To constraint particular vessel / vessel schedule in order release during planning

$
0
0
Hi,

We need to constraint particular vessel / vessel schedule in order release during planning

Example:

Order Release:
271239

Carrier: LSP (CAR-12301)

Vessel schedules available:
1. 20120511_LSP_RUS_1512_RUHJD_USPOA
2. 20121101_RUSJ_LSP2_HJSD_1191D_RUHJD

While bulk plan / show route option, system is always picking vessel schedule: 20120511_LSP_RUS_1512_RUHJD_USPOA

However, we want to plan through vessel schedule: 20121101_RUSJ_LSP2_HJSD_1191D_RUHJD

Since, shipments planning is done on wrong vessel, we need to change all details manually on shipment to correct the vessel details like ETD,ETA etc.

So, how we can achieve this in OTM; any pointers would help us to break through

Thank you


-Prasad-