consolidation Deconsolidation pool scenario

Hi All,

I am doing Consolidation & Deconsolidation Scenario With 5 locations A,B,C,D,E and F. C location is the Consolidation Pool and D location is the Deconsolidation pool. its planned successfully. as per scenario its create 5 shipments.
like:
A to c
b to c
c to d
d to e
d to f

But 6 shipments were created
like:
A to c
b to c
c to d
C to d
d to e
d to f

i checked in shipments two shipments ware created between C and D locations. here only one shipment create na because C location is consolidation pool so A and B orders are consolidate and plan

Please let me know,
In above scenario how many shipments are created 5 or 6?
if 6 shipments are right, what is the reason for created 6 shipments?
if 5 shipments are right, what is the process for this scenario?